Thursday, 23 April 2015
Annual Report 2014
The latest update on the ongoing monitoring at Wimbish is now available. Click to view here.
Thursday, 15 December 2011
Certified !!
We've just heard that the certification of all the units came through yesterday from the PHI in Germany. Obviously really pleased to get this seal of approval, and plaques for the buildings are now on order, (to be fixed with thermally bridge free fixings of course!)
The Wimbish Experience days are going really well, and I understand we are now full until April. The feedback from the tenants has been absolutely wonderful, it's so good to hear them talk about the low fuel bills and comfort of the homes. I know we always knew it, but when a tenant tells you how wonderful they are and that her gas bill for 6 months was just £30, even in the really cold snap we've just had, I think the whole team can allow themselves just a small element of self-satisfaction.
I've put some images here of the finished product, although of course landscaping always takes some time to have an effect.
Our next 14 passivhaus are well underway at Ditchingham and we look forward to a similar result there.
Chris Parsons
Parsons + Whittley Architects

The Wimbish Experience days are going really well, and I understand we are now full until April. The feedback from the tenants has been absolutely wonderful, it's so good to hear them talk about the low fuel bills and comfort of the homes. I know we always knew it, but when a tenant tells you how wonderful they are and that her gas bill for 6 months was just £30, even in the really cold snap we've just had, I think the whole team can allow themselves just a small element of self-satisfaction.
I've put some images here of the finished product, although of course landscaping always takes some time to have an effect.
Our next 14 passivhaus are well underway at Ditchingham and we look forward to a similar result there.
Chris Parsons
Parsons + Whittley Architects

Thursday, 27 October 2011
Monthly Visitor Experience proves to be great success
Following the first two successful visitor experience sessions and due to high demand we have released additional dates in 2012. The sessions feature presentations from Hastoe and the architect Parsons & Whittley, along with an opportunity to view three of the house types.
VISITOR EXPERIENCE: LIMITED SPACES AVAILABLE: Contact Angela Davis or Jackie Deane AT HASTOE ON 01799 533 170 OR EMAIL eastdev@hastoe.com:
- 6 March 2012
- 3 April 2012
- 8 May 2012
- 12 June 2012
Frequently asked questions and answers coming soon.
Ulrike Maccariello, Hastoe Development Manager
Tuesday, 12 July 2011
Rural communities do lead innovation
As residents move in to our completed Wimbish Passivhaus project, we feel very proud to have worked with Wimbish Parish Council and the community to show that affordable homes in rural villages can make positive changes to the way we approach design and build; to protect the climate and tackle rural fuel poverty.
Investing in this exemplar scheme, at an additional cost of 10%*, has taught us a great deal about what we can achieve in our future programme. The lessons learnt are already being replicated on site at our second Passivhaus development in Ditchingham, Norfolk and the uplift costs have been limited to 6%*. We will be developing more Passivhaus schemes after that.
This experience has proved that overcoming the challenges associated with developing homes for local people, in sensitive rural areas, can go hand in hand with cutting edge techniques. We’re pleased to be supporting the National Housing Federation’s Rural Housing Week (11-15 July) and showcasing Wimbish as part of that.
We’re also hosting a monthly visitor experience from September, to share more about the project with professionals from the sector and I hope you might be able to join us on one of the dates shown below:
Sue Chalkley, Chief Executive, Hastoe
*determined by comparison to an equivalent Code Level 4 development in the Hastoe programme.
VISITOR EXPERIENCE: LIMITED SPACES AVAILABLE: Contact Angela Davis or Jackie Deane AT HASTOE ON 01799 533 170 OR EMAIL eastdev@hastoe.com:
· 6 September 2011
· 4 October 2011
· 8 November 2011
· 6 December 2011
· 10 January 2012
· 7 February 2012
· Further dates 2012 will be announced in due course
Sue Chalkley, Chief Executive, Hastoe
*determined by comparison to an equivalent Code Level 4 development in the Hastoe programme.
Friday, 25 March 2011
TSB funding secured for in-depth study
I’m really pleased to say that Hastoe has secured funding from the government-backed Technology Strategy Board to monitor the in use performance of our Passivhaus homes.
It was one of only five domestic projects, along with ten non-domestic projects, to be successful in its application to the second round of the Building Performance Evaluation Competition, open until 2012.
We’re now into the next stage of planning for the monitoring of the development which will take place over the next couple of years. This monitoring will enable questions like the following to be explored:
· Is running the buildings as cheap as it has been designed to be?
· How much does the energy use vary between homes, and how does the difference break down?
· Are comfort levels and air quality maintained in all homes through all seasons?
· Is the solar thermal system effective in providing hot water and heat?
· Are residents happy with the heating and ventilation systems?
To answer these, we will be looking at:
· The handover of the properties to residents
· How residents use the technology, following on from early training with Hastoe
· Full monitoring every few minutes, every day of
o the temperature, humidity and CO2 levels in several rooms
o the external temperature, humidity and sunshine
o all hot water flows in the heating system, together with the electricity used
o the quantity of gas, electricity and water used by each house
o energy consumption of the ventilation system and air flow temperature
o sub-metering to determine where electricity is being consumed.
The study will fully monitor one unit from each block; that is one three bedroom house, one two bedroom house, and one flat. The remaining 11 units will have reduced monitoring that will help provide an even wider knowledge base, and to provide context for the more in-depth research. The utilities and the internal environment of one room will be monitored; sub-metering and electricity used by the heating and ventilation will be recorded.
Looking at the project so closely will mean we can learn a lot, and share these lessons across the construction and housing sector as the results are collated.
We’ve been supported in the application by Build with CaRe, an international project aiming to help mainstream low carbon construction in the EU. They’ve been monitoring low energy homes since 2009 and in the East of England partner with the University of East Anglia, West Suffolk College and Southend-on-Sea Borough Council.
This monitoring project will make it possible to share the true benefit of Passivhaus principles and promote low carbon construction in housing.
You can find out more by seeing our full release here.
Ulrike Maccariello, Development Manager, Hastoe
Friday, 18 February 2011
Initial Air Testing
Dominic had skilfully mounted the Wincon unit in a panel and fixed it into the door opening, and wound the pressure up to 50 Pascals to see what was giving. Initial testing just by hand highlighted some problem points in the ceiling Intello membrane, and a few leakages around Internorm's factory fitted Illbruck tape but on the whole nothing really surprising. Sealing of a few service penetrations was happening whilst the test was underway and then a closer investigation with a smoke pen highlighted some more suspect areas.
The boffins will work out the actual air leakage on a rough and ready measure over the next few days, but at least we have started to find the weak spots in the design/construction before we plaster.
The other exciting development was to see the insulation being fixed in earnest. This has been delayed for a couple of reasons but now that it is underway the buildings start to take on a bit of texture as the windows settle into the cosy covering of 285mm of Springvale's Platinum EPS. With a Lambda of 0.030, this, coupled with the rest of the wall construction, will give a U value of 0.080, making it the most thermally effective wall we have ever undertaken.
We also showed a journalist from Greenbuild magazine around this afternoon, and talked to her at some length, (my friends down the pub already call me a passivhaus bore!), about the project, the challenges we have faced, and the issues the scheme has presented, but on the whole, still a positive experience and a sense of expectation is gathering as more and more of the final elements fall into place.
Chris Parsons
Tuesday, 8 February 2011
Weather relents and progress regained!
So, once the weather relented in January we were at last able to make some real progress on site. Firstly the external insulation was fitted between the rafters to allow the roofing to continue. Fiddly this with the extended rafter foot needing to be accommodated within the insulation zone, but essential to maintain progress.
Then window fitting could proceed at last, and some experts from the supplier soon had these in place. Remarkably this seems to transform the site and it begins to take visual shape. Extended protection has been applied to protect the PPC finish, and the extended sills look exposed awaiting the insulation placement.
Insulation placement has been a problem as both air and surface temperatures need to be above 5 degrees, so maybe January wasn't the best time to try and do this, but things are warming up and so hopefully we'll soon be wrapped up nice and warm.
The photo here shows the air tightness tapes around the window and door frames before sealing to the walls, and the DAS tape at the junction of the wall to the floor. All of these get plastered in so as to link to the air tight plaster membrane.
Then window fitting could proceed at last, and some experts from the supplier soon had these in place. Remarkably this seems to transform the site and it begins to take visual shape. Extended protection has been applied to protect the PPC finish, and the extended sills look exposed awaiting the insulation placement.
Insulation placement has been a problem as both air and surface temperatures need to be above 5 degrees, so maybe January wasn't the best time to try and do this, but things are warming up and so hopefully we'll soon be wrapped up nice and warm.
Fortunately it is not on the critical path, so Bramall have been busy internally, first fixing mechanical and electrical, including the MVHR ducts.
Further work has been going on as well on completing the various membranes and tapes in preparation for an initial, pre-plaster air leakage test. Although the plaster is our actual air leakage membrane, it is felt worth testing before plaster to see if there are any unforeseen areas that may need attention. Bramall have purchased their own 'hovercraft' as it is known and we anxiously await the first test results.
And I can't sign off without congratulating the Bramall site team on the quality of the catering at site meetings which is much improved since my first blogged comment!
Ahh, the power of the internet!!
Chris Parsons
Parsons + Whittley Architects.
Feb 2011
Wednesday, 26 January 2011
Interim certificates confirm site on course for Code 4
All the units on the site have been issued with their design stage Interim certificates under the Code for Sustainable Homes (May 2009) and are on course to get their final certificates once complete.
The Code 4 pass mark of 68 percent has been comfortably exceeded with dwellings scoring between 72 and 77 percent. Although not outstanding in itself these results are particularly pleasing given that there are tensions between the Code and Passivhaus that make some credits harder to achieve.
These areas include:
• Secured by design (Man 4) – although Passivhaus windows and doors (Internorm Edition are being used at Wimbish) have excellent locking mechanisms they do not have the SBD approvals that is often required by police Architectural Liaison Officers.
• Global Warming Potential of insulation (Pol 1) – nearly all insulation used on the site has a GWP of less than 5 but the German Passivhaus loft hatch supplier was unable to provide any evidence of this. Consequently the credit could not be achieved.
• Responsible resourcing of materials (Mat 2 and 3) – many of the materials were sourced from suppliers where the necessary certification could not be guaranteed and so the Code strategy set early in the project was to not pursue these credits. It is likely that a number of credits could have been achieved if necessary. More ‘Code compliant’ products could have been used but these often do not have the certification required for Passivhaus.
• Energy and Carbon (Ene1) – a gas heated Passivhaus should achieve a good score in this area but there are a number reasons why this is not the case. Firstly there is a well recognised problem in the Code with flats and mid terraces whereby the small amount of external surfaces makes it hard to show significant carbon reductions through insulation measures. The flats only narrowly achieved the necessary 44% reduction in carbon emissions (block average). PV could have been added if really necessary for Code compliance but this would not have helped Passivhaus performance since it focuses on rewarding demand reduction. Thirdly the non-standard (for the UK) heating strategy of a thermal store supplying a wet heating coil in the MVHR supply air duct cannot easily be entered in the SAP calculation making it hard for the likely carbon reductions to be recognised in the calculations.
These issues will all be resolved in time as the supply chain recognises the importance of both sets of certification. More products and UK suppliers in particular will all help to push down the cost of achieving Passivhaus in the UK.
Nick Jones, Associate Director, Inbuilt
The Code 4 pass mark of 68 percent has been comfortably exceeded with dwellings scoring between 72 and 77 percent. Although not outstanding in itself these results are particularly pleasing given that there are tensions between the Code and Passivhaus that make some credits harder to achieve.
These areas include:
• Secured by design (Man 4) – although Passivhaus windows and doors (Internorm Edition are being used at Wimbish) have excellent locking mechanisms they do not have the SBD approvals that is often required by police Architectural Liaison Officers.
• Global Warming Potential of insulation (Pol 1) – nearly all insulation used on the site has a GWP of less than 5 but the German Passivhaus loft hatch supplier was unable to provide any evidence of this. Consequently the credit could not be achieved.
• Responsible resourcing of materials (Mat 2 and 3) – many of the materials were sourced from suppliers where the necessary certification could not be guaranteed and so the Code strategy set early in the project was to not pursue these credits. It is likely that a number of credits could have been achieved if necessary. More ‘Code compliant’ products could have been used but these often do not have the certification required for Passivhaus.
• Energy and Carbon (Ene1) – a gas heated Passivhaus should achieve a good score in this area but there are a number reasons why this is not the case. Firstly there is a well recognised problem in the Code with flats and mid terraces whereby the small amount of external surfaces makes it hard to show significant carbon reductions through insulation measures. The flats only narrowly achieved the necessary 44% reduction in carbon emissions (block average). PV could have been added if really necessary for Code compliance but this would not have helped Passivhaus performance since it focuses on rewarding demand reduction. Thirdly the non-standard (for the UK) heating strategy of a thermal store supplying a wet heating coil in the MVHR supply air duct cannot easily be entered in the SAP calculation making it hard for the likely carbon reductions to be recognised in the calculations.
These issues will all be resolved in time as the supply chain recognises the importance of both sets of certification. More products and UK suppliers in particular will all help to push down the cost of achieving Passivhaus in the UK.
Nick Jones, Associate Director, Inbuilt
Thursday, 23 December 2010
Site Visits Extended! Plus, FAQs
Due to overwhelming demand the project team have decided to facilitate an additional open event day at the Passivhaus site in Wimbish in February. The open event will provide a brief presentation followed by a walk around the site. Time for questions and answers will be at the end. The event is free but restricted to 15 attendees and a maximum of 2 people per organisation. The event booking is on a first come first serve basis. For enquiries and bookings please contact umaccariello@hastoe.com
Upcoming Events
Tuesday 4 January 2011 – FULLY BOOKED
Tuesday 1st February 2011, 1.30pm to 4pm
The open events we held in November and December were really well attended and even though we had a few late cancellations due to the snowy weather condition in early December we were able to fill most spaces at the last moment.
Nick Jones of Inbuilt and Chris Parsons of Parsons & Whittley are doing a fantastic job with their presentations. They provide an interesting and informative overview of the Passivhaus principles and provide some specific examples in regards to Wimbish. The December site walk around was rather brief due to the freezing conditions and everybody appreciated the hot cup of tea or coffee back at the village hall.
The discussions back at the village hall provide a great opportunity to get further valid information and here are just some of the frequently asked questions:
Q: What are the cost implications in comparison to a conventional building?
A: Hastoe’s cost consultant Davis Langdon is currently undertaking a cost comparison to some of Hastoe’s Code Level 4 schemes and this information will be available on the blog soon
Q: What happens if people want to fix items like pictures or shelves to the walls?
A: Fixing to internal walls is not a problem as long as the occupants fill the wholes with a wall plug and screw. Hastoe will need to ensure that following any tenancy change wholes left will be filled to re-instate the airtightness of the building.
Q: You have explained that the construction method at Wimbish is thin joint blockwork with an external insulation and render finish. This sounds like a standard construction method used in England?
A: The approach for Wimbish was to use local materials where possible and local labour, and it is indeed correct that this method is not ground breaking and is widely used, but the standards for a Passivhaus do need to be to a much higher.
Ulrike Maccariello, Development Manager, Hastoe
Tuesday, 21 December 2010
Arctic weather slows progress
I've been anxiously hoping to add something to the blog of value over the last month, but frankly the weather has beaten us all and I think it's unlikely to relent before Christmas. Our last site presentation included only a restricted walk round the site because so much of the site and scaffold was frozen and icy. Hopefully the visits and presentations have been informative, we certainly get some good feedback. See other blog entries for more details on these.
The blocks are now all complete in terms of superstructures, and felt and batten is halfway there but the weather has even held that up!
Windows have arrived and everyone is very excited by the quality of the product, even though they still sit securely in the container. Given that they are already triple glazed, they are quite heavy, (hence the debate regarding fixings), and manouvering them on an icy site may be problematic.
The external insulation has also arrived so we really just need the weather to clear and we can get progress moving again.
It looks like we have secured a great monitoring arrangement with the UEA and we shall be installing some telemetry in one of each of the different units to provide feedback on the energy use of the properties, hopefully over a two year period.
In the meantime, Happy Christmas to all our readers and we look forward to reporting real progress in the new year!
Chris Parsons
Parsons + Whittley
The blocks are now all complete in terms of superstructures, and felt and batten is halfway there but the weather has even held that up!
Windows have arrived and everyone is very excited by the quality of the product, even though they still sit securely in the container. Given that they are already triple glazed, they are quite heavy, (hence the debate regarding fixings), and manouvering them on an icy site may be problematic.
The external insulation has also arrived so we really just need the weather to clear and we can get progress moving again.
It looks like we have secured a great monitoring arrangement with the UEA and we shall be installing some telemetry in one of each of the different units to provide feedback on the energy use of the properties, hopefully over a two year period.
In the meantime, Happy Christmas to all our readers and we look forward to reporting real progress in the new year!
Chris Parsons
Parsons + Whittley
Thursday, 4 November 2010
All Trussed Up
The whole team rolled up their sleeves to help the adjacent village hall recently by re-decorating the outside of the hall as a thank you for their patience whilst we disrupt their car park and access. Luckily the sun shone, and the brilliant white paint caused several instances of reflected sunburn! There should be some photos on the gallery page.
The build is proceeding well, with the roof trusses going on to plots 1 - 6 and 11 - 14. Plots 7 - 10 will shortly follow. The large overhang on the eaves required for additional shading has been designed in two parts to break up the mass a little and there has been some discussion on site regarding the best fixing methods, but that is all now pressing ahead. We are wondering whether to fit some of the eaves insulation during the roofing process to ensure a quality fit and to make sure there are no gaps.
We had the first of a series of open meetings to show interested parties around on Tuesday, (2nd Nov), and the contractor kindly laid on guided tours after we (Parsons + Whittley) and Inbuilt had given presentations in the village hall on the principals of Passivhaus and their interpretation at Wimbish.
The windows should be arriving soon, and when these are fitted we plan an early pressure test to see how we are doing. You wouldn't believe the discussion around the window fixing detail, although for those who have built Passiv before, you probably would! The remaining membranes, tapes and grommets all need to be fixed pre-plaster so that we can detect any weak spots in the strategy.
Weekly design meetings on the site are helping to resolve issues before they arise, although the tea and biscuit supply to these meetings is taking far too low a priority in my view.
Chris Parsons
Parsons + Whittley Architects
The build is proceeding well, with the roof trusses going on to plots 1 - 6 and 11 - 14. Plots 7 - 10 will shortly follow. The large overhang on the eaves required for additional shading has been designed in two parts to break up the mass a little and there has been some discussion on site regarding the best fixing methods, but that is all now pressing ahead. We are wondering whether to fit some of the eaves insulation during the roofing process to ensure a quality fit and to make sure there are no gaps.
We had the first of a series of open meetings to show interested parties around on Tuesday, (2nd Nov), and the contractor kindly laid on guided tours after we (Parsons + Whittley) and Inbuilt had given presentations in the village hall on the principals of Passivhaus and their interpretation at Wimbish.
The windows should be arriving soon, and when these are fitted we plan an early pressure test to see how we are doing. You wouldn't believe the discussion around the window fixing detail, although for those who have built Passiv before, you probably would! The remaining membranes, tapes and grommets all need to be fixed pre-plaster so that we can detect any weak spots in the strategy.
Weekly design meetings on the site are helping to resolve issues before they arise, although the tea and biscuit supply to these meetings is taking far too low a priority in my view.
Chris Parsons
Parsons + Whittley Architects
Tuesday, 2 November 2010
UK Passivhaus Open Days
The Wimbish Passivhaus development will be open on Friday 12th November as part of the first ever UK Passivhaus Open Days.
The construction site will be open for pre-booked visits at the following times: 11am, 12noon, 2pm and 3pm.
Advance booking only through Jane Barnes Jane.Barnes@davislangdon.com
Visitors will need to bring their own safety equipment (boots and hard hats).
Sunday, 17 October 2010
Up to floor joist
As it took a while to get the website and blog up and running, my first blog comes as we await the first floor PC slabs for the flats. For historical purposes, 400mm of Dow Floormate was placed without difficulty beneath the 300mm RC rafts, and the insulation is now all nicely wrapped up and backfilled. All the service penetrations were installed ready to receive air tight grommets and the blockwork commenced.
Most Passivhaus’s in the UK are built by enthusiasts for enthusiasts, but at Wimbish we are trying to build them in a normal commercial volume house building environment. That means getting your everyday subcontractor to understand the process and the importance of quality and detailing that wouldn’t normally apply in this environment.
Initially this included making sure the Aircrete thin joint blockwork was laid fair face to the outside rather than the inside, as the insulation has to be fitted later with no air gaps between the sheets.
Our air tightness barrier is to be the wet plaster but where we pass through the first floor void the ground and first floor plaster skins are linked by a Solitex Plus airtight membrane. Initially we had proposed PC slabs even in the houses because of the ease of obtaining this air tight seal, but value engineering changed this to timber posi-joists which present a few more challenges, particularly with restraint straps and in the corners. Several mock ups and some significant time and effort on site has been expended to ensure this is properly placed and installed.
So, the PC slabs should arrive on Monday for the 6 flats and then we can speed ahead to getting the roof trusses on. The next passivhaus task will be the air tight membranes at ceiling level, and then maybe a preliminary air test before plaster to see how we are doing.
Parsons + Whittley Architects
17th October 2010
Friday, 15 October 2010
Site Visit Opportunity
Hastoe Housing Association in conjunction with the project team are facilitating a series of open events at the Wimbish Passivhaus site. The open events will provide a brief presentation followed by a walk around the site. Time for questions and answers will be at the end. The events are free but restricted to 15 attendees per event and a maximum of 2 people per organisation. The event bookings are on a first come first serve basis. For enquiries and bookings please contact umaccariello@hastoe.com
Upcoming events:
Tuesday 2 November 1.30pm to 3pm
Tuesday 7 December 1.30pm to 3pm
Tuesday 4 January 1.30pm to 3pm
Upcoming events:
Tuesday 2 November 1.30pm to 3pm
Tuesday 7 December 1.30pm to 3pm
Tuesday 4 January 1.30pm to 3pm
Ulrike Maccariello, Development Manager, Hastoe
Tuesday, 5 October 2010
Welcome!
Welcome to the Wimbish Passivhaus blog. Along with our partners, we hope you find the information here and on our website a useful insight into this exciting example of how innovation and advanced building techniques can work for rural affordable housing. Hastoe is committed to the climate change protection agenda and we will learn a lot from this scheme – we intend to share this across the sector and take what we learn forward, to reduce the carbon footprint of all our new homes. We look forward to receiving your comments.
Sue Chalkley, Chief Executive, Hastoe Housing Association.